BEN 4 Project Component

Since this component represents a significant portion of the required budget, will take the longest to complete and is the most complex of the entire plan.

The project is a brown-field cement plant with a capacity of 3,600 tonnes per day of clinker. That equates to 1.2 Million tons pa of cement.

The Benghazi 4 line includes a crusher for limestone and mixbed, new raw mill and raw meal silo, clinker transport to existing clinker hall, kiln, cooler, process filter, precalcining and chloride by-pass, and feed from existing homo silos to new preheater. The scope also includes auxiliary equipment such as water treatment, compresed air, electrical additions and central control room.